SAP C-TS412-2021 certification exam is a globally recognized certification that is highly valued by employers. SAP Certified Application Associate - SAP S/4HANA Project Systems certification demonstrates that a professional has a deep understanding of SAP S/4HANA Project Systems and can effectively implement and manage solutions in this area. Professionals who hold this certification are highly sought after by organizations that use SAP S/4HANA Project Systems.
NEW QUESTION # 37
Dates
How are earliest dates and latest dates of activities schedule?
- A. Earliest dates are scheduled by backward scheduling, and the lates dates by copying the earliest dates.
- B. Earliest dates are scheduled by forward scheduling , and the latest dates by backward scheduling.
- C. Earliest dates and latest dates are scheduled by forward scheduling.
- D. Earliest dates are scheduled by backward scheduling, and the latest dates by forward scheduling.
Answer: B
NEW QUESTION # 38
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.
- A. WBS element
- B. BOM item
- C. Material master
- D. Network activity
Answer: B,D
NEW QUESTION # 39
Which object is relevant in assembly processing to create an assembly order for the SD document?
- A. Item category
- B. Requirement class
- C. Control key
- D. Project profile
Answer: B
NEW QUESTION # 40
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct answers to this question
- A. Saving a goods receipt
- B. Saving a supplier invoice
- C. Saving a service entry shee
- D. Saving a purchase order
Answer: A,C
NEW QUESTION # 41
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?
- A. Enter an offset of 10 days to the start date of the activity.
- B. Enter an offset of -18 days to the finish date of the activity.
- C. Enter 10 days as duration.
- D. Enter February 10 as fixed date.
Answer: D
NEW QUESTION # 42
Revenues & Payment
A customer use cross- company - code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal .. correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?
- A. Split the project intdifferent project according to each company code.
- B. Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly.
- C. Change the project structure so that it correspond better to the company's organization structure.
- D. Settle the WBS element to the highest billing element before you do the result analysis.
Answer: C
NEW QUESTION # 43
Which planning method can prevent further rescheduling of activities?
- A. Partial confirmation of activities
- B. Capacity requirements activation
- C. Capacity levelling
- D. Workforce planning
Answer: A
Explanation:
Partial confirmation of activities is a planning method that allows you to confirm a part of an activity's duration or work. This prevents further rescheduling of the activity because the confirmed part is fixed and cannot be changed. The remaining part of the activity can still be rescheduled according to the project progress and resource availability. Reference: https://help.sap.com/viewer/0c9a2f8f9c1b4a2e8b3f7d0c9b6e1d8a/2020.000/en-US/4c5f7a3e6b571014e10000000a174cb4.html
NEW QUESTION # 44
Project Structures
Which the following statement regarding networks are correct?.
Note : there are 3 correct answers for this question.
- A. During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity.
- B. Capacity requirements of a network activity are reduced when the activity is confirmed.
- C. You can assign the same work center to more than one activity on the same network.
- D. If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.
- E. You can assign more than one activity element to a network activity.
Answer: B,C,E
Explanation:
"You can assign more than one activity element to a network activity." According to SAP Help Portal, "Capacity requirements of a network activity are reduced when the activity is confirmed." According to SAP Press4, "You can assign the same work center to more than one activity on the same network." Reference: 4
NEW QUESTION # 45
You want to assign milestones to WBS elements. For what can you use these milestones? Note: There are 2 correct Answers to this question.
- A. For trend analysis
- B. To set an actual finish date for WBS elements
- C. To transfer the actual date to the billing plan
- D. To start workflow tasks
Answer: A,C
NEW QUESTION # 46
You are working with networks and WBS elements. Which of the following statements applies
- A. You can reassign an activity from one network to another
- B. You have to maintain a network profile in the project profile
- C. You can assign the network header to multiple WBS elements
- D. You have to activate the operative indicator Account Assignment Element for WBS element with activities.
Answer: D
NEW QUESTION # 47
What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.
- A. A delivery document type must be configured.
- B. A sold to party is necessary.
- C. A shipping point is necessary.
- D. A sales order must be created in advance.
Answer: B,C
NEW QUESTION # 48
What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are 3 correct answers to this question
- A. Generate purchase requisition
- B. Generate delivery
- C. Stock transfer posting
- D. Confirm production order
- E. Cancel goods issue
Answer: A,C,E
Explanation:
Project-Oriented Procurement (ProMan) supports various business transactions that are related to project procurement. Some of these transactions are:
Stock transfer posting: You can use this transaction to transfer project stock from one storage location to another within the same plant or between different plants.
Generate purchase requisition: You can use this transaction to create a purchase requisition for a material or service that is required for a project.
Cancel goods issue: You can use this transaction to reverse a goods issue posting for a material that was issued from project stock. Reference: https://help.sap.com/saphelp_erp60_sp/helpdata/EN/8e/8bc95360267214e10000000a174cb4/frameset.htm
NEW QUESTION # 49
You want to determine the planned costs for an internally processed activity. Which data do you need Note: There are 2 correct answers to this question
- A. Work
- B. Profit center
- C. Activity type
- D. Duration
Answer: C,D
Explanation:
To determine the planned costs for an internally processed activity, you need the duration and activity type data. The duration is the time required to complete the activity. The activity type is a classification of activities according to their functions or characteristics. The system calculates the planned costs for an internally processed activity based on the formula for costing in the work center, the activity output price for the activity type and cost center assigned to the work center, and the duration of the activity. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 50
How can you confirm the working hours of different work centers for a single activity?
- A. Enter multiple work centers within a single confirmation.
- B. Enter direct activity allocation assigning multiple work centers.
- C. Create multiple confirmations for the activity and use the appropriate work center for each confirmation.
- D. Assign multiple work centers to the activity.
Answer: B
NEW QUESTION # 51
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this question
- A. Actual revenue is posted via a billing plan assigned to a WBS element
- B. Actual revenue is posted via a billing document created from a sales order
- C. Planned revenue requires a sales order assigned to a WBS element
- D. Planned revenue can be transferred from a sales quotation
Answer: A,D
NEW QUESTION # 52
The__________________that you specify when you create a project definition is unique for the entire project. Choose the correct answer.
- A. Controlling area
- B. Plant
- C. Company code
- D. Planning department
Answer: A
NEW QUESTION # 53
......
SAP C_TS412_2021 exam is an excellent opportunity for professionals who want to demonstrate their expertise in SAP S/4HANA Project Systems. SAP Certified Application Associate - SAP S/4HANA Project Systems certification is recognized globally and can help individuals advance their careers in project management, planning, and execution. With the right preparation and dedication, passing the exam can be a significant achievement for any SAP professional.