NEW QUESTION # 32
You are using budgeting and active availability control. How can availability control be activated? Note: There are 2 correct answers to this question

  • A. Automatic activation with assignment to an investment program
  • B. Automatic activation with the first actual posting
  • C. Automatic activation with budget assignment
  • D. Background activation (CJBV - Activate Availability Control) l

Answer: C,D


NEW QUESTION # 33
Which objects can be used to specify settlement rules? Note: There are 2 correct answers to this question?

  • A. WBS elements
  • B. Network activity for activity-account-assigned networks
  • C. Network header for activity-account-assigned networks
  • D. Standard WBS elements

Answer: A,B


NEW QUESTION # 34
When you create a service activity in your network, what data can be entered? Note: There are 3 correct Answers to this question.

  • A. Material master within service specification
  • B. Service specification
  • C. Vendor
  • D. Service purchase order number
  • E. Overall limit (maximum value of all unplanned services)

Answer: B,C,E


NEW QUESTION # 35
Project structure.
You intent to work with predefined project coding mask to create project definitions. What do you have to consider?

  • A. You can create project coding mask X... event if there are project numbers beginning with X.
  • B. You can use only numbers for a project coding mask definition.
  • C. The standard project definition must differ from the definition of the operative project.
  • D. You can use an indicator to determine that only coded project numbers may be used within the project system.

Answer: D


NEW QUESTION # 36
A customer needs to analyze the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct answers to this question

  • A. Cost element reports
  • B. Hierarchical reports
  • C. Structure information system reports
  • D. Resource reports

Answer: B,D

Explanation:
Resource reports and hierarchical reports are some of the possible reports that you can use to analyze the capacity requirements of your network activities. Resource reports display capacity requirements and availability for work centers or resources over a period of time. Hierarchical reports display capacity requirements and availability for work centers or resources in a hierarchical structure, such as plant, MRP controller, or work center group. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 37
In your logistics project, you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?

  • A. Capacity planner group in the network header
  • B. Scheduling and capacity category
  • C. Control key of an activity
  • D. Scheduling and distribution key

Answer: C


NEW QUESTION # 38
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct Answers to this question.

  • A. The material master of the component must permit project stock management.
  • B. A procurement indicator must be assigned to the activity.
  • C. The network activity is assigned to a WBS element.
  • D. The network is assigned to a sales order item.
  • E. The Project Stock indicator is set in the project definition (non-valuated or valuated).

Answer: A,B,E


NEW QUESTION # 39
Which organizational structures are required for network activities? Note: There are 3 correct answers to this question

  • A. Plant
  • B. Sales organization
  • C. Operating concern
  • D. Company code
  • E. Controlling area

Answer: A,D,E

Explanation:
Controlling area, plant, and company code are some of the organizational structures required for network activities. Controlling area is an organizational unit that represents a closed system for cost accounting purposes. Plant is an organizational unit that represents a location where materials are produced or services are provided. Company code is an organizational unit that represents an independent accounting entity with its own balance sheet and profit and loss statement. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 40
Which of the following statements apply to project versions? Note: There are 2 correct Answers to this question.

  • A. Project versions can be changed.
  • B. Project versions are mandatory for Milestone Trend Analysis (MTA).
  • C. Project versions can be created automatically based on user status.
  • D. Manually created project versions always require a project version profile.

Answer: A,B


NEW QUESTION # 41
How are earliest dates and latest dates of activities scheduled?

  • A. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling
  • B. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling
  • C. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates
  • D. Earliest dates and latest dates are scheduled by forward scheduling

Answer: A

Explanation:
Forward scheduling is a method of scheduling activities from the start date of the project to the end date. Backward scheduling is a method of scheduling activities from the end date of the project to the start date. The earliest dates are determined by forward scheduling and the latest dates are determined by backward scheduling. This ensures that the activities are scheduled within the project duration and that any slack time is distributed evenly. Reference: https://help.sap.com/viewer/0c9a2f8f9c1b4a2e8b3f7d0c9b6e1d8a/2020.000/en-US/4c5f7a3e6b571014e10000000a174cb4.html


NEW QUESTION # 42
Which statement is valid regarding networks?

  • A. Relationships can be used to connect activities of different networks
  • B. Material components can be assigned to activity elements
  • C. A network can be activity-account-assigned and header-account-assigned
  • D. A network activity can be assigned to several WBS elements

Answer: A

Explanation:
One statement that is valid regarding networks is that relationships can be used to connect activities of different networks. Networks are structural elements of a project that represent processes or operations within a project. Networks consist of various activities that represent tasks or partial tasks within a network. Relationships are logical connections between activities or networks that define the sequence or dependency of their execution. Relationships can be used to connect activities of different networks in order to model complex processes that span across multiple networks. For example, you can use a finish-start relationship to indicate that an activity in one network cannot start until an activity in another network is finished. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 43
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?

  • A. Activity
  • B. Milestone
  • C. Network header
  • D. Activity element

Answer: A

Explanation:
To maintain constraints for start dates, you can use activities. Activities are structural elements of a network that represent tasks or partial tasks within a project. Constraints are parameters that define fixed dates or time intervals for activities or networks. Constraints can be used to influence the scheduling of project objects and to ensure that certain deadlines are met. You can maintain constraints for start dates or finish dates of activities or networks in the project builder or the project planning board. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 44
Material
You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason?
Note : there are 2 correct answers for this question.

  • A. The item category of the materials is set tstock item.
  • B. The material have no material number.
  • C. The procurement type in the material master is set to in-house Production.
  • D. The item category of the materials is set tnon-stock item.

Answer: A,C


NEW QUESTION # 45
You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order .
What do you have to consider?

  • A. The maintenance order s must be assigned to the same budget profile as the project definition.
  • B. The maintenance orders must be assigned as sub-networks.
  • C. The maintenance orders must be assigned to the same plant as the network.
  • D. The maintenance orders must be assigned to WBS element.

Answer: C


NEW QUESTION # 46
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?

  • A. The person responsible for the work center
  • B. The person responsible for the network activity
  • C. The MRP controller for the network
  • D. The person responsible for the superior WBS element

Answer: C


NEW QUESTION # 47
What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this question

  • A. A delivery document type must be configured
  • B. A sold to party is necessary
  • C. A sales order must be created in advance
  • D. A shipping point is necessary

Answer: A,D


NEW QUESTION # 48
......